Hi,

Having an interesting problem at the moment, we have PIR's created in ECC that are then reprisented by FC Req's in APO, so all is as expected.

The issue that I am having is that if I copy the active version for a simulation version the FC Req's are being shown as Dep demand!!

Have I missed something on the copy back process?

Plus I have noticed that if for example the FC Req is for 10 in the active version not only does it change the element type but also splits the order down (as if rounding was being used) so I end up with 5 dependent demands of 2.

Thanks in advance.

Edited by: UKuser on Nov 19, 2009 2:38 PM

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

1)For forecast coming as Dep demand, check whether the

ATP categories, category groups are transferred

correctly from active to simulation version.

2) Check the logs of copy version jobs which will give

some insight to you to act accordingly

3) For splitting of demand, check whether the lot size,

product split etc., are maintained accordingly and

transferred correctly

Regards

R. Senthil Mareeswaran.