Hello,

I'm configuring the ERM, and when creating an role in the ERM I try the "risk Analysis" it says that there is no risk (Risk Analysis performed successfully; No risks found). I know that there is a risk, and it still give me ok.

Why is it giving me OK?

The tcodes are FD01 & VA01.

In the miscellaneous I have it configured "Do not use Web Service; CC deployed on the same server " for the Web Service Info. for CC Risk Analysis

Best Regards.

Pablo Mortera.

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Yes, we have executed those steps.

Former Member
0 Kudos

Hi Pablo,

Have you run a simulation in RAR directly?

This would help to prove whether the issue resides in the RAR rules or in the integration of this with ERM.

If this works in RAR on it's own, then try specifying the webservice for RAR and testing that connection.

Simon

Former Member
0 Kudos

Hi Pablo Mortera..

1) Did you successfully completed the background jobs in ERM

Org Value Sync

Transaction/Object/Field Sync

Activity Sync

In the same sequence.

2) RAR did you generated the rules...

3) in RAR all the background job sync is completed?

FULL user sync

FULL role sync

FULL profile sync

Management reports update.

Regards

Gangadhar