Scheduline Agreements and link with MRP

Former Member
0 Kudos

Dear All,

I have a problem in creating scheduline agreements ,

As per the cilent requirement,

The scheduline lines recevied by the client are of two types with the difference name as "Shippment Date and Delivery Date"

here they define Shippment date and Delivery date as follows:

Shipment date is the date that the material which will be leaving from the plant from the shipping point.

Delivery date is the date that the material will be reaching at the customer hand

here the problem is for delivery date

if the delviery date is mentioned in the customer PO ,

then the user who is entering the schedulines in the schedulines agreeement he has to take into account the date

( six weeks before that ) . in order to make the production person to run MRP based on this date.

1. Do the user has to calculate manually the dates and enter in the scheduline coloumn or

*2. If the person is entering the dleivery date (wht ever given by the customer ) in the schedulines. how will the system will calculate automatcially six week before the delviery date to RUN the MRP

there is no problem with Shipment Date.

the shipment date will be entered as it is, and based on that MRP will be run

Accepted Solutions (0)

Answers (2)

Answers (2)

reazuddin_md
Active Contributor
0 Kudos

Shipment date is the date that the material which will be leaving from the plant from the shipping point.

In SAP, GI date is the date, when the goods leaving from the Plant premises.

Delivery date is the date that the material will be reaching at the customer hand

Delivery date, specifies the date , when goods will be expecting at customer site ( this date will be determined from GI date + Transit duration in Route master).

1. Do the user has to calculate manually the dates and enter in the scheduline coloumn or

No need to calculate the dates manually. This Calcuation will be done based on your customization in Route Master ( Transit Duration). but delivery dates has to be entered manually in Schedule lines tab in Scheduling agreements.

*2. If the person is entering the dleivery date (wht ever given by the customer ) in the schedulines. how will the system will calculate automatcially six week before the delviery date to RUN the MRP

Based on Delivery date/ GI date/ Pick pack & load time = Material available date will be determined. This Material available date then transferred to prodcution.

reazuddin_md
Active Contributor
0 Kudos

Shipment date is the date that the material which will be leaving from the plant from the shipping point.

In SAP, GI date is the date, when the goods leaving from the Plant premises.

Delivery date is the date that the material will be reaching at the customer hand

Delivery date, specifies the date , when goods will be expecting at customer site ( this date will be determined from GI date + Transit duration in Route master).

1. Do the user has to calculate manually the dates and enter in the scheduline coloumn or

No need to calculate the dates manually. This Calcuation will be done based on your customization in Route Master ( Transit Duration). but delivery dates has to be entered manually in Schedule lines tab in Scheduling agreements.

*2. If the person is entering the dleivery date (wht ever given by the customer ) in the schedulines. how will the system will calculate automatcially six week before the delviery date to RUN the MRP

Based on Delivery date/ GI date/ Pick pack & load time = Material available date will be determined. This Material available date then transferred to prodcution.