on 11-19-2009 6:16 AM
Hi experts
The business requirement is as follows:
1) Project schedule option-1 with work packages and costing plan ( L1 schedule)
2) Project schedule option-2 with different work packages and relevant costing plan (L2 schedule)
Clien requires both of these as drafts
The requirement can be met by creating sim_ver1 and sim_ver2 in transaction CJV1 (with out having operative version).
Subsequently the approved sim version will be used for creating operative version.
But is it possible to maintain cost plan for sim versions?
If no, please suggest best practice.
warm regards
ramSiva
You can only use network costing for simulation version. Other cost planning methods are not possible for simualtion version. Refer SAP Help
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.