Hi,

1. I have a scenario of working with Material deteriminations.

2. NOw i have to also plan for the rescheduling of sales order with V_V2

3. The sales order with the material deterimnation are not listed in this rescheduling.

4. I also read from sap help the below

Rescheduling

When you reschedule (transaction V_V2), orders that contain items determined in product selection are reevaluated. If the substitution settings have changed, or there is more product available, the system may determine other substitutes. This may result in products being promised to the customer other than those agreed to at the time of order entry. To avoid this, you can set the fixed date and qty indicator in the order (choose Goto ® Item ® Schedule lines). The system will not take the order account when rescheduling.

Items determined in product selection are only considered in a rescheduling run when you have set the input parameters to include all materials. If you specify only certain materials, main and sub-items from product selection are excluded.

The fixed date and quantity indicator does not influence product selection in the delivery.

If a product selection item has been partially delivered, the system does not take it into account in rescheduling runs.

5. i could not figure out the issue.

6. Kindly let me know the solution.

Dsk

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

HI,

When u rescedule then on intial screen remove tick mark from simulation.

If u are using material determination or product determination then run rescedule for products which u are determined in sales order.

kapil

Dsk
Active Contributor
0 Kudos

closed as no reply