Hi Guys,
I have one issue please do needful, Inspection lot transferring from quality loc to another quality loc within plant iam using QAc2 (This is working) but I want to split the inspection lot quantity I need to transfer another location.
Is it possible to create new inspection lot from Existing insp lot @ different location for Partial Qty??
Jay
not answered
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Jayashankar
Can you let us know what is the need of moving the stock to 2 storage locations
Regards
Gajesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
There is one solution for this apart from the inspection lot creation.
While taking UD in stock posting screen,While putting Quantity to Unrestricted you can change storage location.
Like say lot size is 100 .
Then in storage location screen put 50 Qty in storage location X
& remaining QTY 50 into storage location Y.
Regards'
Sujit
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear
What I said was.......lets say material is in QI stock.You have taken UD & Total material moved to unrestricted.
Now you want to post the QTY say half into sLoc Y.
From unrestricted move half the material to Sloc Y by MB1B-->311 mvt type.Here you activate 08 inspection type.Lot of 08 inspection type will be created.Take UD & post material to SLoc Y.
I hope I have made it clear.
Also what first option suggested was much more simpler than this one.
Regards'
Sujit