on 11-18-2009 5:51 AM
Hi,
I am having the below scenario.
We have QM active in our plant. In the material master records we assign two inspection types '01' - Goods receipt insp. for purchase order & '08'- Stock transfer inspection. I didn't make any inspection plan (QP01).
We make a Purchase order ( say Qty=10)with excisable tax code. While doing GR (MIGO) for the purchase order, we capture and post Excise Invoice. Later, Usage Decision is done using QA11(7 qty to unrestricted stock type & 3 Qty to Blocked Stock). Later, i want to send the blocked stock to the vendor, I am transferrring the material from Blocked stock to QI stock type using MT349. But, system is showing the below warning message : 'Preparation for the quality inspection could not be comleted. -Message no. QA187'.
Please let me know how we can change the status of the inspection lot from 'Created' to 'Released' so that I can proceed further making the Return delivery to vendor using T.Code: MIGO.
Thanx in advance.
Regards,
Phani
Hi
Check the Usage of the Task list.
Check the date of creation of task list must be prior to creation of lot.
Go to QA02
Inspection specification > Assign task list by click on Task/ specification
Go to Sample, do the SAmple calculation
Save
Check whether lot status is Rel
Regards
Sujit
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
CREATE inspection plan for that material with usage 9 or see in spro settings what is the uasge maintained for 08 inspection type.
then go to qa02 open that insp. lot and attached this inspection plan through "task list assignment " save
status of inspection lot will change from crtd to rel.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
110 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.