on 11-18-2009 12:41 AM
Folks
I am in SCM 2007 / 5.1, SNP heuristic is used for planning certain components.
SNP heuristics does not consider Purchasing Contract as a source of supply.
Is there a way to create Pur Req with reference to Purchasing contract from SCM?
OR
Is there a mass reassignement program on ECC to change the source of supply from Inforecord to Contract for Pur Req?
Hi! Rex,
by standard hueristic planning PR cannot be created as per the cotract.
we also had the same requirment but we did it as follows.
we created the Purchase Req. as per hueristic logic which flow to ECC.
then through a custom program we stamp the contact detail in the purchase req.
& when we do Purchase Req- Purchase Order conversion through ME59N the system convets only the Contract permitted quantity
Regards
Vaibhav Sareen
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
8 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.