Subcontracting BOM in CN52N?

former_member283293
Participant
0 Kudos

Hello Experts,

I have a multilevel subcontracting BOM (materials with special procurement key 30) where I have placed the top component in the WBS structure and run MRP.

The BOM explodes and all levels can be seen in MD4C. But when I try to use CN52N to get an overview of all the components, I can only see the top level.

Is there a way to adjust this report so that it will also display my subsequent requirements?

Or is there another report than I can use?

rgds

GAR

Accepted Solutions (0)

Answers (2)

Answers (2)

former_member283293
Participant
0 Kudos

Hello,

The reservation for the material comes from the top material of the BOM which is entered into the WBS-structure. The rest of the BOM have subsequent requirements which MRP creates purchase requisitions to meet.

We run all materials in project stock.

All our materials have no entry in the individual/collective requirements filed

rgds

GAR

Former Member
0 Kudos

Hi,

Before execution of MRP, you may have raised/ put a requirement for the material from Project ( say as creation a reservation for the same). So can you tell me which is that material for which you may have created a reservation. Secondly, the dependent items of the BOM for subcontracting, is it having collective requirment or individual requirement in their respective masters.

Regards

Avisek Bhardwaj