on 11-17-2009 10:30 AM
Hi all,
we decided to manage a settlement profile, already used at 100% validation and % settlement, also at amount settlement.
So I setted the flag 'Amount settlement' in the settlement profile. In the actual settlement rules it appears correctly the new Column 'Amount'.
The column 'Amount' doesn't appear in the planned settlement rules. Currently the plan settlement can be managed only at percentage. Is this the standard? Isn't possible to settle the planned costs with the amount? Must I set some other parameters to use the plan settlement with amount?
Thanks for your help,
Jessica
Refer This Note 113629 - Information: Plan settlement before and as of Release 4.5
The same is SAP Std. behaviour. Plan settlement with amounts is still not possible.
My mistake initally i have given you wrong note no. Please refer above note.
With Regards
Nitin P.
Edited by: Nitin Patoliya on Nov 17, 2009 4:19 PM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
110 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.