my client is using planning buckt profile with 2 years of horizon.
in that 2 years first year should be plan in months and weeks..
for next year it is planning only in months...
how could i do in the planning bucket profile???
Hi dallyanusha,
Make your settings of PBF as follows:-
Number of Basic Fiscal year Display Fiscal year
periods periodicity variant of perio- variant of
basic period dicity display periodicity
2 - - Y -
1 Y - M -
Regards
R. Senthil Mareeswaran.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi dallyanusha ,
Ur requirement is still confusing. As in one of the earlier thread u have written that u dont want to plan for the first week of a month where the start date is WEDNESDAY and the plan should be from the 2nd week onwards for that month. But in this thread u havent specified that. If the earlier requirement is not so much relevant to u then the reply given by Mr.Senthil is appropriate and u should be able to get ur desired results using the workarounds which he has given.
Otherwise u need to maintain Fiscal year variant( as per as ur requirement, i.e excluding the week where the first day of the month is WEDNESDAY). And u assign that FYV in ur Planning Bucket profile.
Regards
Sunshine
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
9 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.