on 11-16-2009 6:10 AM
Hi all
Has any one worked on revenue budgets in ps ?
How this can be handled in ps?
Revenue budgets consist of revenue recipts and its expendetures. Usually expendetures from this type of budgets does not result in creation of assets.
shashank
Hi shashank22 ,
Check the below link It ma help to you.
http://help.sap.com/saphelp_47x200/HELPDATA/EN/aa/96853478616434e10000009b38f83b/frameset.htm
I think you first create cost element group for revenues and make it Planning be Revenue cost elements wise.
Path: Project System->Revenues and Earnings->Planned Revenues->Manual Revenue Planning->Structure Planning
CJR9 PS: Display Revenue Element Planning
CJ42 Change Project Revenues
CJ43 Display Project Revenues
Regards,
Kishore K
Edited by: kishore babu on Nov 18, 2009 11:31 AM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
92 | |
11 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.