Hi, We face the problems regarding bom explode in CK11N:

1) we have a costing variant(PPC1) which can explode the BOM from the other plant.

2) The special procurement type for cross plant = '40'.

3) We know that standard SAP will base on Special procurement will explore the cross plant bom, but now we want to create a new costing variant which don't explode the BOM from the other plant. Is any user exit or modify the Standard SAP function to control the explore BOM.

Thanks,

Best regards,

Simon Ong

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

I have knowledge on transaction CK11N but I do not understand what BOM means?

Regards

valérie

Former Member
0 Kudos

Thanks for your inquiry, the BOM = Bill of Material, please refer to http://help.sap.com/saphelp_47x200/helpdata/en/a0/1016bd4c8311d189520000e829fbbd/frameset.htm for details information:

******************************************************

BOMs (PP-BD-BOM)

Definition

A formally structured list of the components that make up a product or assembly. The list contains the object number of each component, together with the quantity and unit of measure.

BOMs are used in their different forms in various situations where a finished product is assembled from several component parts or materials. Depending on the industry sector, they can also be called recipes or lists of ingredients and so on.

They contain important basic data for numerous areas of a company, for example:

MRP

Material provisions for production

Product costing

Plant maintenance

You can create the following BOMs in the SAP system:

Material BOMs

Equipment BOMs

Functional location BOMs

Document structures

Order BOM

Work breakdown structure (WBS) BOM

Selection Criteria

Selection is necessary if you plan production in the R/3 System or if you want to maintain BOMs for technical objects from the area plant maintenance. If very large documents about BOMs are to be cumulated in the document management system (DMS), you also have to select the se components.