Hi all,

I followed the process explained in Building Block S16 for PP and did following steps,

created characteristic, assigned values and assigned to a class of type 019

Assigned them to the two work centres and to operation in the recipe

then tried cifing. It cifed, but only components and operation. No activity cifed. While CFM2 log message says no activity in operation for the PV.

In recipe only one operation and a phase exists. Also in the recipe, I assigned one of the workcentre. Hope this is the way it should be..

Looking for help

Thanks

Edited by: Vardev on Nov 14, 2009 4:04 AM

Edited by: Vardev on Nov 14, 2009 3:52 PM

Hi all. I found out the reason. No process time defined for the phase. Simple mistake.. but took my well over 2 hrs.