Hey Gurus,
We are planning and releasing scheduling agreements in APO through the product view. The problem that we are having is that we can't see these released schedule lines in MD04 after the schedule lines are released in APO. Is there somethign with the CIF that needs to be set up for this? We already have integration models set up for PIR's and SchAgreements already.
Also, we checked the /SAPAPO/CCR reconciliation report and didn't see anythign stuck in there Do you guys have any suggestions for us?
Sincerely,
Kris
Hi Kris,
Please check the the distribution definition has been maintained for each location
SPRO:
Integration with SAP Components
Integration via APO Core Interface (CIF)
Basic Settings for Creating the System Landscape
Basic Settings for Data Transfer
Publication
Maintain Distribution Definition
Publication type: "confirmaiton for scheduling agreement"
Regards
Julien
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Kris.
Did you check if your object is included in any Integration Model? You can do that in Transaction CFM5.
Search for the object and then click the button "Models" to check if any activated model appears.
Also, run report RAPOKZFX to check for problems with the field APOKZ in MARC table.
Hope this helps you!
Have a nice week!
Will
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
9 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.