Hi Experts,
May I kindly ask if there is a way that a workcenter be selected for a material depending on the specific Finished Good linked to the Material (SFG. Problem is the material is located in one plant only.
Here is the case Scenario:
1. Two Finished Goods are produced in the same plant but in different locations.
2. Both Finished Goods are using the same Semi Finished Good
3. The Semi Finished Good used by both FG has only 1 material number
4. There are 2 workcenters producing the Semi Finished Good
5. The Work Center that will be used by the Semi Finished Good depends on the Finished Good that will be using the SFG.
Is there a way that the Work Center can be selected during the creation of Planned Order depending on the Finished Good that will be using the SFG? That there will be 2 primary resources depending on who will use the SFG?
Really hoping for your kind help. Thank you in advance.
Sincerely,
Ria
Hi Ria,
You can implement BADI /SAPAPO/PWB_SOS to determine or select a resource .
Work centers are resources in SCM.
You can see further details in T code SE18
SAP description of this BADI:
BAdI: Change Source Determination
Use
This Business Add-In (BAdI) is used in the component Sources of Supply.
It enables you to do the following for the "valid sources of supply"
determined by the system:
o Change the sorting
o Change the data for a source
Example
The system is to take the valid sources into account as follows:
o When a procurement order is created in the background, sources with
the procurement priority 3 are not to be taken into account.
o When a procurement order is created in dialog mode, sources with the
procurement priority 3 are to be displayed as additional procurement
alternatives.
To achieve this result, proceed as follows:
In mode P (planning in the background), filter out the sources with the
procurement priority 3 by deleting such sources from the table
CT_SOURCES_EXTEND.
The parameter IV_LOW_LEVEL_CODE within the method PWB_USEX_SOS indicates
whether the BAdI has been called up within the determination of the
low-level code. If so, the parameters IV_MINLS and IV_MAXLS are not
filled.
Thanks,
Pavan Verma
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Ria,
I think it can be achieved through PPDS huristics.
Run SAP_PP_002 (Standared lot size) huristics by using propagation range and propagate the SFG to the specific resource through propagation range. Try it and let me know the results.
Hope This helps.
Regards,
Kishore Reddy.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
9 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.