Hi,

In VTAA,QT TO OR ,I want to change the copying requirements in schedule line to 501But 501 routine is not available.How to do that..

Rgds,

Pavan.

Accepted Solutions (1)

Accepted Solutions (1)

Lakshmipathi
Active Contributor
0 Kudos

You can create a routine in VOFM

thanks

G. Lakshmipathi

Former Member
0 Kudos

Hi SIr,

How to create a routine after getting into VOFM.Pls suggest..

Rgds,

Pavan

Former Member
0 Kudos

After going to VOFM, in the menu bar you can see different tabs like copying requirements, data transfer,requirements etc, select which type of routine you want, and click the tab, its self understandble then...

thanks,

Raja

Former Member
0 Kudos

Hi,

I got it.But how to active the routine...I want to activae 501 routine..

Pavan.

Former Member
0 Kudos

Hi,

ok.I got answer.Thanks..

Answers (2)

Answers (2)

reazuddin_md
Active Contributor
0 Kudos

501 is a std routine, its already available in SAP. Which version you are using. These routines can be deleted after deactivation the respecitve routines in VOFM. Check is there any deletion of routines occured?

Former Member
0 Kudos

Hello

Go to VTAA

Select QT-OR

Select schedule line cat -BN

Right bottom -copying requirement is maintained. 501.

Former Member
0 Kudos

Hi,

501 routine is nt available inside..

Rgds,