on 11-13-2009 7:03 AM
Hi Experts,
With total 7 planning versions and total size of 9GB, the data cache is constantly filling up
Total 14GB allocated and each time we create a new version the usage goes up by 10%.
There are no old sessions more than 4 hrs and when 5 planners starts working simutaneously, the cache starts filling up
Thanks,
Naren
> With total 7 planning versions and total size of 9GB, the data cache is constantly filling up
>
> Total 14GB allocated and each time we create a new version the usage goes up by 10%.
>
> There are no old sessions more than 4 hrs and when 5 planners starts working simutaneously, the cache starts filling up
Now what?
You create multiple versions of liveCache objects in parallel - of course the cache usage will increase (and also the used space in the data area).
That's how the multi-version-data-handling works.
A copy of the current version is created for each new version.
So either add more cache, reduce your planning version complexity/size or do less in parallel if you want to prevent the cache from beeing used 100%.
regards,
Lars
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
82 | |
10 | |
10 | |
9 | |
6 | |
6 | |
5 | |
5 | |
4 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.