Creating Change Request from project structure

Former Member
0 Kudos

Hello.

Have somebody maked somthink like creating Change Request from Implementation project configuration structure? I want to initiate new change request directly from busines process step in transaction SOLAR02 for example.

Accepted Solutions (0)

Answers (2)

Answers (2)

raguraman_c
Active Contributor
0 Kudos

Hi,

You can create an Issue and further to that you can create a Change Request being in SOLAR01/SOLAR02 only.

Go to tab Issue/Msssage you can create new Issue there, where you can see a tab Change Request. You can create your Change request from this tab.

Hope this solves your issue.

Feel free to revert back.

-=-Ragu

prakhar_saxena
Active Contributor
0 Kudos

Hi

Change request is created via action Create change document from support desk message

so in solar02 tcode...goto issues/messages tab and create a message then

crm_dno_monitor you can create a change request as i said and all the necessary data like ..system data,ibase etc is copied to ur change req from support message .

Regards

Prakhar

Former Member
0 Kudos

Thanks for reply.

Yes, I know this. But it is necessary to create Change Request dirrectly from project with defined executor of concrete developing task