on 11-12-2009 9:33 AM
Hi Guru's,
We are using IS Auto for our production planning. We are using IPPE in ECC and using Model Mix Planning for detailed sequence plan. This this being currently implimented and running well for sometime.
Now client wants to impliment APO SNP solution for their supply network planning. Now we have basic doubts regrding the system constraints like for SNP we need source of supply as PPM / PDS. But in IS Auto we are using IPPE as a source of supply. Have enquired also, not many people are using SNP and IPPE both. Can someone through some light into it.
done
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Priya,
SNP will not work with Variant configuration scenario. If u implement SNP, it will work stand alone.So as per ur business requirement u can take the call whether to implement SNP or not.
Regards
Sunshine
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
8 | |
3 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.