Hi Experts,

I am trying to use partial lot in production(04). But I could not get it. Please help on this issue

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Sandeep

As per SAP standard, you cannt use partial lot for 04 inspection origin. Why do you want to use partial lot in 04? whats your requirement?

Former Member
0 Kudos

Thanks for your answer. Even from SAP I have got the same message that for 04 insp.type partial lot not supported.

Thanks a lot experts

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi

Which T code you are using to create a partial lot.Please elaborate your problem.

As per my understanding it's CO11 or CO15 is used to created partial confirmation which will create partial lot.