We do have a CPP system running on SAP ECC 6.0 version.

1. In SLD, we do have the list of all "Software Components" used in CDP.

We do not have the "PRODUCT VERSION" of the managed system.

2. With job SAP_SLD_DATA_COLLECT (RZ70), all data are sent from CDP (managed system) to SLD.

3. With LANDSCAPE FETCH job, all data are synchronized between SLD and SMSY.

Now, how can we choose the right "PRODUCT VERSION" to set in SMSY ?

As far as there is not "PRODUCT VERSION" defined in SLD, do we have to set manually a PRODUCT in SMSY ?

Is there any guide or OSS Notes which describe, step by step, the full workflow process synchronization

from (1) Managed System to (2) SLD to (3) SMSY ?

Thanks

Best regards

PC

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

As I have observed, when the data sync happens between SLD and SM system, the product versions are also assigned.

Sometimes, the product assigned through SLD sync may not be correct or may be irrelevant to your scenario,

In that case, you should always manually edit and assign the correct product version in SMSY, to avoid any conflicts arising in further setup of EWA, SMD setup etc.

For ECC 6.0, you can goto SMSY>systems>search for SAP ECC-->your system CPP/CDP should already be present under SAP ECC through SLD landscape fetch job.

Select that system, and in the header data tab u can see the Installed product versions.

There you can always change the relevant products for your systems.