Hi,

In MDM 7.1 how many hosts are actually needed to run a MDM-SRM scenario? Do you need all five (import server, syndication server, mdm server, layoutserver and dbms) or is it enough with one mdm server that hosts the whole MDM solution? And if so, does the SRM catalogue require a seperate server, or does it run on the same server as a regular EP server? Im feeling a bit confused in this whole MDM environment thing atm.. please help out

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Naim

For answer your question you should provide more information about your plans.

For example:

if you haven't plan to do import master data automatically- import server is not needed

if you haven't plan to do syndicate master data automatically - syndication server is not needed

if you haven't plan to do product catalog - layout server is not needed

Regards

Kanstantsin