Hi Gurus,
I have a issue where the PO is not appearing for confirmation when searching for the time range in the confirmation screen.
But while giving the PO no., i am getting the the PO details for process confirmation.
It is not appearing within the time range.Also partial GR is done for the PO.
I have checked all the cheks(del completed, etc....) but of not much use.
Can any one help in this matter.
Resgards
IS
.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Are you using process confirmation or Central confirmation.
If central receiver role you are using as per the standard sap only limits 500 hits.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Indu,
check OSS Note 1240482 and 1177963 .
Hope the above note helps.
Cheers
Iftekhar Alam
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.