I am working on Easy cost planning for WBS elements.

I am using the PS06 costing varient, and cost planing version 0.

In Easy cost planning it is showing the values per the planning forms, but the same is not getting reflected in cost reports.

CJE0 - plan/actual reports

Thanks,

Srihari.G

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

You can run CJEN and reconstruct your project info database after it run your cost reports again.

Best regards

Jose Marin

Former Member
0 Kudos

Thanks for the reply, after running CJEN, values are reflecting properly

Thanks once again

Karthik

Former Member
0 Kudos

CJEN did it for me too. Thanks for your post

Edited by: kennyk on Nov 10, 2009 12:28 PM

Answers (1)

Answers (1)

former_member201206
Active Contributor
0 Kudos

Hi Srihari,

It sounds, that the value catagorie customizing is not set correctly, which map the cost type to the cost catagorie.

There is a help transaction rakcshow, which enable you to have a deep look of the data record. Run this transaction with the WBS, and check COSSA, COSPA and RPSCO. If the record of RPSCO is missing, then it is problem with value catagorie.

Kind regards,

Zhenbo

Former Member
0 Kudos

Thanks for the reply,

I am not able to run the help transaction you have told. is there any other way

thanks