cancel
Showing results for 
Search instead for 
Did you mean: 

Activity Delay

Former Member
0 Kudos

hi,

I have Plan for my Project Initially.

There are three activities,I Partially confirm the Second activity of which 50 % work is completed and then it gets delayed for two months.

Now after two months I want to start the activity from the rest 50 % as of Today and do scheduling

How to Map this scenario?

Thanks,

Nitin

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Dear Experts,

Please Update

Thanks,

Nitin

Former Member
0 Kudos

Hi,

After partially confirming the activity try using Constraints. I have not tried this scenario although. Its just a wild guess.

Regards,

Gokul