on 11-09-2009 12:48 PM
Hi SCM Guru,
We are small organization and we are implementing DP and PPDS without SNP.
Is it possible to release DP directly to PPDS?
Thanks in advance,
Jay
Hi,
Since you are planning to deploy PPDS, I assume you have R/3 to integrate with. In that case its better release the DP demand to R/3 through transfer profile and bring it to PP/DS through the CIF route as PIR. By this method, creating planning area, planning book etc will not be neccessary.
If the above case is not true and you want APO to be deployed as standalone, then go by SNP route.
Thanks,
Rajesh Manoharan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Jay,
The Planning area 9ASNP02 controls both SNP & PPDS.
So, you can release your DP results into PPDS
But you need to ensure that the key figure, planning
bucket profile, planning area are selected as per PPDS
basis and do the release.
Your master data set up also to be aligned as per PPDS
requirements (say like resources, capacities etc.,)
Regards
R. Senthil Mareeswaran.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Jay,
You can do that as you will release forecast to SNP planning area (Create planning area with SNP flag) which you can use in PPDS.
Regards,
Kishore Reddy
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
13 | |
4 | |
3 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.