Hi SCM Guru,

We are small organization and we are implementing DP and PPDS without SNP.

Is it possible to release DP directly to PPDS?

Thanks in advance,

Jay

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Hi,

Since you are planning to deploy PPDS, I assume you have R/3 to integrate with. In that case its better release the DP demand to R/3 through transfer profile and bring it to PP/DS through the CIF route as PIR. By this method, creating planning area, planning book etc will not be neccessary.

If the above case is not true and you want APO to be deployed as standalone, then go by SNP route.

Thanks,

Rajesh Manoharan

Former Member
0 Kudos

Hi Jay,

The Planning area 9ASNP02 controls both SNP & PPDS.

So, you can release your DP results into PPDS

But you need to ensure that the key figure, planning

bucket profile, planning area are selected as per PPDS

basis and do the release.

Your master data set up also to be aligned as per PPDS

requirements (say like resources, capacities etc.,)

Regards

R. Senthil Mareeswaran.

Former Member
0 Kudos

Hi Jay,

You can do that as you will release forecast to SNP planning area (Create planning area with SNP flag) which you can use in PPDS.

Regards,