Component Assignment to Activity

Former Member
0 Kudos

Hi

I am facing one issue regarding material assignement to network activity, When I assigned the material to activity then option 'NEVER' is populated for Reservation/ Purchase Requisition. I want this should be with option 2 ( From Release).

I have checked network profile also & here I had consider the option 2 ( From Release).Is there any other place where we set this setting. Please share your valuable opinion.

Regards,

Ashok Sangal

Accepted Solutions (0)

Answers (2)

Answers (2)

nitin_patoliya
Active Contributor
0 Kudos

There is not othere place it will pick from network profile only, just chech you are referreening correct netowrk profile only.

With Regards

Nitin P.

virendra_pal
Active Contributor
0 Kudos

in network profile select as required