We have some project activities that should be capitalized, and some that are not. The issue is that we would
like to use just one network profile, so it means one network type, and I am not sure if individual activities can
have different settlement profiles, if not maintained for the network type.
Also while WBS can be linked to investment profile, can not see the same for the network type, not to mention
the activity level.
So, can it be still managed with a single network profile and a single network type?
use WBS as a differentiator not NWA
keep cap WBS (with investment profile) and non CAP WBS (without investment profile) seperate
now do your activities as usual with settlement to respective WBS
settle to AuC is always done from WBS for Cap WBS and cost centre or elsewhere as required for non cap WBS
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I believe we cannot settle activity cost to WBS AUC, we have to settled to WBS , when you settle the first time WBS all the acumulated cost settled to WBS. Here you have to segregate you capitalized cost and non - capitalized cost. Create two settlement rule one of AUC and other for Cost center.
Please refer below link.
http://help.sap.com/erp2005_ehp_04/helpdata/EN/4c/2273a946e611d189470000e829fbbd/content.htm
With Regards
Nitin P.
Hi Nitin,
I believe I can settle directly from the network activity to AuC (not the WBS AuC, but just manually created AuC) for capex, and elsewhere for Opex (to the Cost Center).
I see no benefit (do you think there is any?) to settle from activities to WBS first and make it two step settlement process.
Thank you.
User | Count |
---|---|
110 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.