on 11-09-2009 11:05 AM
I have a network activity that is processed by different work centers.
For example SAP blueprint activity is performed by the Finance team (Work Center), P2P, Sales & Distribution team.
Same for Testing activity and so on.
I do not want to split the same activity per team (Work Center), but require the team information to be visible in the matrix reporting.
Another option would be to manage it as one Work Center, but then how to segregate between different workstreams?
Thank you for your input!
you can set up activity elements under a network activity and assign different work centres to each activity element
or you can set up different activities for different work centres
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Well, for consistency reasons I do not want to get down to activity elements, as everything in CATS is now managed at activity level. Let us assume there is just one work center, but there is a business requirement to report its resources splitted by sub-team. Is there any additional field that can bring in such additional dimention for analysis?