on 11-09-2009 10:43 AM
Hi All,
I have bee trying to unlock the Network which is locked but not able to do so. The error is "The transaction 'Unlock' is not allowed for NWA because no status is set to permit it". I have checked that there are no user statuses and the network has a single activity. The status of the activity is REL CNF MCNF SETC.
Regards,
Laxminarsimha
This message was moderated.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
check if the WBS to which the network is attached has a status ending with LK
e.g. AALK, MDLK etc
if so unlock that
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
So, Network header is locked , You need to unlock the network header, As you told while unlocking network header you are getting errors. There is some inconsistency with your the system status. As you already cleared but re-check, click on I system status button and chekc is there any user status profile is assigned to any of network , activity , WBS.
One more strange thing is that your network header is having LKD status and the same is not passed on to your activity.
With Regards
Nitin P.
I am still not convinced with your answer, can you check in OK02 the assigned status profile and chekc for the forbid business transaction.
Do one more check, if there is no userstatus has been activated as you told than Technically system will allow yo to delete the status profile , Try to delete the both the status profile & Let see how system behaves ?
A/c to your error is pointing, some user status is activated on PS Objects. Just chekc it out.
With regards
Nitin P.
in project builder
select network header (has LKD status - right)
now select the blue i button next to system status
select tab business process
scroll to business process unlock assignment and tcik the box on the left (should be red in your case as you cannot unlock)
seelect button transaction analysis
can you see any status with RED????
In Business processes tab, 'unlock & unlock assignment' are in green colour. When I selected 'unlock' and clicked on transactional analysis, I can see the message as status 'LKD' is allowed. For 'unlock asssignement', statuses 'LKD' and 'REL' are allowed.
I can see the foloowing in red colour
Actual activity allocation
Actual overhead (periodic)
Actual settlement
Automat. WIP/results analysis
Change
Change automatically
Check PRT availability
Check material availability
Close
Complete back to tech complete
Confirm order
Hi,
I have replicated this issue. The steps are
1) Set 'LKD' status at network header level, it automatocally sets 'LKD' at activity level
2) Now go to planning board, select the activity. Goto Edit>Status>Unlock Account assignment. It will remove 'LKD' status from activity.
3) Now try to unlock the header, system does not allow to do so.
If step 2 is not performed then header can be un locked.
How would I unlock the network header
Regards,
Laxminarsimha
Praveen,
We exactly have the same issue . And when i search for the OSS note you mentioned (1694139), it says that the note doesn't exist. If i am correct , was that a note or OSS message number (1694139) solution from SAP ? If you dont mind sharing the correction program provided by SAP, would really appreciate it. I am working on creating a message with SAP on this issue too.
Thanks