Dear all expert,

could you help me on the following issue?

i create a project in CJ20N, i use internal activity and external activity.

the materials to be procured are assgined to the internal activity, i release the project, run project MRP and the PRs for materials generated.

as for the external activity, i use it to generate the service PR to be procured from outside.

therefore, there are two kinds of PRs in the project.

as far as i know, the PR No are generated automatically.

but i want to find a way to tell they are two kinds PR, for example, from PR No or other way.

can you give me some help on suggestions?

thanks a lot.

Judy

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

To add to Gokul's Comments, in ME5J if you put item category as D, you will get only service related PRs.

or you can filter for service related PRs after executing the report.

Answers (1)

Answers (1)

Former Member
0 Kudos

HI,

Try ME5J.

Regards,

Gokul