How to link Network Activities AND Order PM Order Operation ?
Ex. Network Activity 0010 -
> PM Order Operation 0020
Please suggest.
Swapnil Kharul
Thanks to all.
Swapnil
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Yes PM Order is some sort of subnetwork under activity 10 of network, ( So, you can schedule it with the higher activity under which order is assigned is the date of the PM Order ) You can achieve these type of Scehduleing with respect to CN24n Overall network scheduling. ) A/c to above scenario if the network operation 0010 is assigned to PM order than in internal activity tab of the network you will find subnetwork (grayes out field ticked )
With Regards
Nitin N.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Virendra and Zhenbo
First of thnks for speedy response.
Virendra - Actualy I am talking about Planning/Scheduling Point of view, wherein I can make dependancies betwn PM Oobject and PS Object (problably Order and Network can be used).
In Planning board of PS -- Order can be display but its operation I am not able to see. Is there any setting/activation ?
Any other way to link those two elements (Relationship: FS, SF,...)
Please suggest.
Zhenbo - I think there should be a way two connect/link two elements as menu path option is available in Network screen.
Please suggest.
Swapnil Kharul
Hi Nitin
PM Order is sub-network of Network this statement is right.
But when I see Network(ctrl+F9) function in Application bar of Network screen, check box is not coming for selection of Order subnetwork object. My requirement is to connect Order operation and Network Activity together.
Please suggest.
Swapnil Kharul
Hi Swapnil,
The answer above explain the accouting assignment view of two order types.
I think, you would like known from logistic point of view or scheduling view. It is not possible to connect two operations\activitiy from different order types. The description of note 427353 give you this information too.
The scheduling of PS (network) and PM integration.
The dates of superior activity of network are handed down to PM order header during scheduling, and then PM order uses this dates schedule it's operations.
Kind regards,
Zhenbo
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
PM orders are not assigned at operation level
assignment of PM order at header level can be done to the network activity
this is the classic difference between PM order (order category 30) and network (order category 20) - PM order can only be header assigned where as for network via configuration we can choose header or activity assignment
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
98 | |
12 | |
10 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.