on 11-09-2009 6:08 AM
Hi Experts
I wish to map the determination of primary and secondary cost elements for
1) Caipital Investment project (asset)
2) Revenue expense project (cost center)
3) Customer project (PA)
I request suggest the configuration tables.
May please provide example
warm regards
ramSiva
not sure of your question
need to set up settlement allocation and source strcutures corrctly to achieve what I think you want
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Yes Verendra Pal
In the absence of CO consultant, i wish to carry out base config for determination of cost elements at Period end closing activities.
I wish to settle for WIP asset as well as for PA.
Any specific document which specifically speaks CO config for PS? Guide me in this aspect.
warm regards
ramSiva
Dear,
You need to create group of cost element by KAH1 as revenue,cost and defined these cost element group in settlement profile in create allocation structure as source and also define settlement cost element here.
And if you want to move these cost to profibility segement or elesewhere then defiene PA transfer structure.in source.
Regards.
Sukhveer.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.