Hi,
I would like to ask.
What is the heterogeneous system copy sequence did you follow?
option1
1) DEV ---> QAS -
> Trial PROD (can be using the exported package of QAS) ---> PROD
Option1 will lead to minimum downtime on PRD. The trial PROD is using a exported package from QAS.
But will this posted a risk of exported failed during the actual export at PRD? Whereby certain item is overlooked.
option 2
2) DEV ---> TRial PROD --> PROD ---> QAS (homogeneous copy).
This will have a longer downtime. Because PROD need to be exported twice.
Is this is the recommendation by SAP heterogeneous guide?
Hope someone has experiences this share with me the information.
Thanks.
CK Chai
Hi,
I will recommend you to check system copy guide on http://service.sap.com.
Also check SAP Note 870863 - Hom. or Het.System Copy SAP NetWeaver 2004s
Thanks
Sunny
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi ,
I have no experience with it. But I know the definitions..
Homogeneous system copy means a system copy with all the database tables from one system to another system of same kind, like same os/db on both the systems.
A Heterogenous System copy is a copy from one system to another system of a different kind, like different os/db in either of those.
Regards
ASADUZZAMAN
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
95 | |
11 | |
10 | |
9 | |
9 | |
7 | |
6 | |
5 | |
5 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.