Hi experts.
We are implementing PS for a mining company; in our process, project designers plan materials and services in networks and then get planned values for budget requests.
The problem I am facing is that I cannot see the planned values from services in the plan values reports. No value is exhibited for version 0 if I plan only services in a network. For materials planning I can visualize planned values normally. The network is not released. On example of planning values report that I am using is s_alr_87013533.
Does anyone know how to correct this problem with PS configuration?
Any help is welcome. Thanks!
Rafael
for planning services I am assuming that you are using service activity
check if determine plan cost is set up in the network header
secondly make sure that the plan costing variant is set up with the valuation variant to define where to get the plan values from
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
110 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.