How can I see planned values for services in PS reports?

Former Member
0 Kudos

Hi experts.

We are implementing PS for a mining company; in our process, project designers plan materials and services in networks and then get planned values for budget requests.

The problem I am facing is that I cannot see the planned values from services in the plan values reports. No value is exhibited for version 0 if I plan only services in a network. For materials planning I can visualize planned values normally. The network is not released. On example of planning values report that I am using is s_alr_87013533.

Does anyone know how to correct this problem with PS configuration?

Any help is welcome. Thanks!

Rafael

Accepted Solutions (1)

Accepted Solutions (1)

virendra_pal
Active Contributor
0 Kudos

for planning services I am assuming that you are using service activity

check if determine plan cost is set up in the network header

secondly make sure that the plan costing variant is set up with the valuation variant to define where to get the plan values from

Former Member
0 Kudos

In fact the problem was in activity control key.

In the control key used for services (transaction OPSU), we activated the "costs" flag and the problem was solved.

Thanks

Former Member
0 Kudos

In fact the problem was in activity control key.

In the control key used for services (transaction OPSU), we activated the "costs" flag and the problem was solved.

Thanks