Network Confirmation

0 Kudos

Hi gurus.

If I confirm a network activity in tcode CN25, the field Actual Finish (time) will be filled with 240000. How can I change this value to the real actual finish time?

Thanks

Accepted Solutions (1)

Accepted Solutions (1)

virendra_pal
Active Contributor
0 Kudos

can you change it when entering the confirmation in CN25??

0 Kudos

No, I can not. The field is invisible and I can not turn it visible in tcode OPUD.

former_member203108
Active Contributor
0 Kudos

Hi,

If your UoM for duration(under scheduling in Internal tab of activity) is day then you wont get actual time field to enter in CN25, If you UoM for duration is Hr then you will see the actual time field.

But still you will get the option of entering actual time for UoM day in CN27(collective confirmation) but not in CN25.

0 Kudos

Ahamed, thanks for your help.