Hi there;

I set-up integration between cProject and FI/CO with PS structure automatic creation after change status (set status "to transferred").

It work well in general, but there is something strange about wbs element code.

Infact, I change cproject project phase number with my own code; ps wbs element don't take this number but the first original number from cProject phase (eg. 19000000000000001542009).

Is this an error or it's normal?

Thanks a lot

Ciao

Luciano

Accepted Solutions (1)

Accepted Solutions (1)

former_member201206
Active Contributor
0 Kudos

HI Luciano,

It works as designed because of the following reasons:

1. The WBS ID in ERP system must be unique.

2. The phase-id in the cProject is NOT unique, you have e.g. same phase-id for two phases.

That is why the replication does not use the phase-id to create the WBS ID. The internal ID of phase is (default ID during creation of a phase) is used for replication

Though there is a Badi method let you change the the WBS ID, but I would not recommend you to do it because of above reasons.

Kind regards,

priyatham_kasu2
Active Participant
0 Kudos

Hi Zhenbo,

Please provide the BADI for changing the WBS ID.

Thanks and Regards,

Priyatham

amit_maheshwari2
Contributor
0 Kudos

The BaDi is DPR_FIN_GECCO_ATTR.

Please check the link as below:

Cheers

Amit