Hello,

I am faced with a scenario where SNP heurestic should consider lead time from product specifc t lane(PDT cifed from Info record) rather means of transport. Is there a setting to do this?

I have cifed across the PIR to APO but the heurestic run is taking duration from means of transport, but I would like to see the duration from prod specif means of transport which has come from PIR

This would be helpful if a vendor supplies multiple SKU's with different lead times.

Thanks for the answer

Bopanna

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Bop

1)Under product specific means of transport in transportation lane, did you

maintain the means of transport.

If it is maintained, system will check the product and means of transport

and concatenate the value and check the transportaion duration

maintained for the product.

2) If you are using VMI scenario, check whether transportation lead time

is maintained in material master of APO in GR/GI tab.

Regards

R. Senthil Mareeswaran.

Former Member
0 Kudos

Hello Senthil,

Would it mean that, I should not maintain MOT at all?

In my current scenario I have maintained MOT and below is the calculation of days that I get

Opening date: Demand date-PDT

Start date: Demand date

End date: Demand date-MOT

I would expect start date=Demand date-PDT

which is not happing now.

Thanks,Bopanna