on 11-06-2009 11:24 AM
Hello,
I am faced with a scenario where SNP heurestic should consider lead time from product specifc t lane(PDT cifed from Info record) rather means of transport. Is there a setting to do this?
I have cifed across the PIR to APO but the heurestic run is taking duration from means of transport, but I would like to see the duration from prod specif means of transport which has come from PIR
This would be helpful if a vendor supplies multiple SKU's with different lead times.
Thanks for the answer
Bopanna
Hi Bop
1)Under product specific means of transport in transportation lane, did you
maintain the means of transport.
If it is maintained, system will check the product and means of transport
and concatenate the value and check the transportaion duration
maintained for the product.
2) If you are using VMI scenario, check whether transportation lead time
is maintained in material master of APO in GR/GI tab.
Regards
R. Senthil Mareeswaran.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Senthil,
Would it mean that, I should not maintain MOT at all?
In my current scenario I have maintained MOT and below is the calculation of days that I get
Opening date: Demand date-PDT
Start date: Demand date
End date: Demand date-MOT
I would expect start date=Demand date-PDT
which is not happing now.
Thanks,Bopanna