How is Processing % of work & Processing % of duration is Calculated in Report CN41
Regards,
Gagan
Processing% of Duration
For the network activity:
Activity is finally confirmed-> Degree of processing duration = 100
Activity is partially confirmed-> Degree of proc. duration = 100 x actual duration divided by (actual duration + remaining duration)
Activity is not yet confirmed-> Degree of processing for duration = 0
For the WBS element:
If no actual finish date is entered-> Degree of processing for the duration = 0
If no actual finish date is entered-> Degree of processing for the duration = 100
Processing% of Work
Activity is finally confirmed-> Degree of processing = 100
Activity is partially confirmed-> Degree of processing = 100 x actual work/forecasted work
Activity is not yet confirmed-> Degree of processing = 0
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
it is based on the confirmation you do for the network
this gets accumulated and rolled up to the top
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
95 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.