on 11-06-2009 8:11 AM
Hello,
We want to consolidate / merger daily planned orders to monthly/weekly using heuristic SAP_PI_001.
We have maintained all the prerequisites as
1. All orders must reference the same production process model
2. All orders must be planned orders
3. All orders must be synchronized, that is, the start and end times of the orders must be the same.
4. All orders must be scheduled at a multi resource with storage characteristics
5. Synchronization must be activated in the master data of the resource
Inspite of this heuristic is not merging the orders. After executing in DS board, we are getting message as Planning executed without any resylt.
Has anybody came across such situations
Will you plz throw some light in this issue?
Thx,
Mangesh
Hi Mangesh,
Check the lot size in material master maintained whether is it periodic lot size.
You need to maintain periodic lot size and mention period type as monthly
alongwith number of periods and then retry
Regards
R. Senthil Mareeswaran.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Mangesh,
SAP_PI_001 can only be run interactively. This answer I got from SAP in a customer message. We afterward tried to create our own algorithm similar to SAP's merge heuristic, but finally figured it was easier to automate this task in R/3.
You can add SAP_PI_001 to the heuristic profile for RRP3, then run it interactively in RRP3 under the variable heuristic button.
Steps:
In RRP3, discover your default heuristic profile Settings>User settings>Profile tab then find the Heuristic profile. Standard in SCM is SAP002 but in your company it might be different.
Then IMG>APO>Supply chain planning>PPDS>Order view>Heuristics in the order view>Maintain Heuristics Profile. Select your default Heuristics profile and add SAP_PI_001.
This heuristic is designed for use in detailed scheduling screen, but I have used it in RRP3. I selected the orders I wanted to Merge, executed the heuristic, and Voila, one order. Naturally, the resulting order must 'fit' in using your existing scheduling strategy, since there are no scheduling settings in the Heuristic itself.
Rgds,
DB49
User | Count |
---|---|
8 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.