PPM CIF error

Former Member
0 Kudos

Hi ALL,

I am trying to cif PPM. I am getting following errors,

'the operation 15 has an invalid control key'

This 15 is a QC phase under the main operation in the recipe. I don't want this in APO and is not scheduling relevant.

Pl let me know how to solve this

Thanks

Mano

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Mano,

1) Check in the operation 15/activity whether the control key is maintained in

the routing

2) Try using sap std control key PP01 and then try

Regards

R. Senthil Mareeswaran.