on 11-05-2009 8:01 AM
Hi Experts
My client constructs a building at customer premises.
What is the best way to map this?
In current plant, to show the customer location as a storage location.
Consume materials and receive building against production order.
At the end of compleition deliver from the same place.
But in reality there is no delivery because the building is constructed at customer place.
Even though, there is no option i believe. We have to show as inhouse production and delivery against sales order.
I request experts to comment.
warm regards
ramSiva
Ram Siva
Use service activity for your requirement. Why are you thinking about production order in your scenario? Are you using any in-house manufactured material in the construction @ client site?
Just use Service activity. Enter the service in service entry sheet & accept it. That's it. No need of any delivery here.
I hope it's clear to you.
Good luck,
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Amol
This solution seems to fit my requirement. Thank you very much.
Shall explore on Asset sale scenario and revert if any query remains.
However, in the above solution, what is the need of service order?.
I will execute a investment project inhouse and settle to an asset. Is it not OK?
You may please detail more, thanks again
warm regards
ramSiva
i would use PS for construction
storage location and plant would be as per MM design if they want to treat customer location as storage location
from PS no issues
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.