on 11-05-2009 5:56 AM
Dear All
I use Easy Cost Planing through CJ20N to plan my cost for project. The planning is on WBS level. It works very well & in reports CNS41 Project cost sch 000 column its show my plan cost correctly but when I go for budgeting through CJ30 I never see my plan cost in Planned Total column. Please can any one explain me where I go wrong or which setting I maintain in customisation
Regards
Nivrutti
My understanding is that easy cost planning cost data will not appear in total Plan cost in CJ30, The reason mostly Easy cost planning is done in other than plan version 0 ( just for preliminary costing purpose ), I doubt if you even dose the same in plan/ actual version 0 then also, it will not come in CJ30 Plan Total ( Click below link for the definition of plan total in CJ30 http://help.sap.com/erp2005_ehp_04/helpdata/EN/fa/74a937016fd743e10000009b38f842/content.htm )
Also check in which version you have done easy cost planning. So, I think it is correct behaviour
Expert Validate my understanding.
With Regards
Nitin P.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Nitin
In my project i use easy cost planing only because i doing cost planing on WBS level. I use plan version 0 only for easy cost planing. My question to you if i do budget for particular WBS if i dont know my planned cost how i do budget for this. I think easy cost planing not only use for preliminary costing it can use also for plan cost at WBS level.
Regards
Nivrutti
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.