on 11-04-2009 1:08 PM
Hi Experts,
My client have 2 company codes with respective plants.
CC01/PL01 and CC02/PL02.
CCO1/PL01 has asked CC02/PL02 to construct a furnace at CC01/PL01.
CC02/PL02 carried out construction activity at CC01/PL01 and handed over.
How to handle this scenario in PS?
Is it has to be mapped as customer project?
If so, construction of funance is to be shown in CC02/PL02 and then finally delivered to CCO1/PL01?
If this is the process to be mapped, it is not right because really the project construction is carried out at CC01/PL01.
How to visualize the project execution at CCO1/PL01? Similarly other logistical aspects like (receipt of material, stocking etc) are realy happens at CC01/PL01. How to visualize this?
I request experts to comment.
warm regards
ramSiva
read sap help
as long as the two company codes are in the same controlling area onlky one project structure is required
in SD you can also look at intercompany billing option or use RRB
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Virendra
Thanks for your reply.
The controlling are is unique.
This scenario can be mapped as a customer project.
But my concern is that, the project is constructed at receipient premises.
How the show the meterial receipts, stock and consumption at receipients premises.
And also about the delivery.
warm regards
ramSiva