Not able to do GR/Confirmation

Former Member
0 Kudos

Hi Experts,

We are using Extended classic scenario 5.0 . For a particular PO we are not able to do GR . And in the confirmation screen that PO was not get displayed.

From the PO, the option " Confirm Performance of Service/Goods Receipt " was got checked and also " No further confirmations expected " was unchecked .

And there is no restrict in the code level i.e badi BBP_WF_LIST.

And there no problem with the roles.

Kindly advice to proceed !!!

Accepted Solutions (0)

Answers (3)

Answers (3)

franz_feichtenschlager
Active Participant
0 Kudos

Also please check whether you could post the GR in ECC using MIGO.

Or do you get any messages??

Good luck

Former Member
0 Kudos

The Status of the PO is in "Ordered" Status and the the option " Confirm Performance of Service/Goods Receipt " was got checked.

Kindly do the needfull

Former Member
0 Kudos

Hi,

I am just hoping that everything is correct and so just run the report BBP_GET_STATUS_2 for the SC and then check in confirm goods and services.

sometime PO gets replicated to ECC but the status is not properly updated in SRM . SRM thinks the PO is still not in ECC and so PO does not appear in confirmation list.

Cheers

Iftekhar Alam

former_member183819
Active Contributor
0 Kudos

check any PO entries in bbp_document_tab table?

br

muthu

Former Member
0 Kudos

Hi All,

I have executed the report BBP_GET_STATUS_2 and there are no entries bbp_document_tab table. Till the problem exists

But when i checked through MIGO , am not getting any messages.

Kindly let me know , how to do confirmation in SRM itself as the customer dont have authorisation to do MIGO.

BR

former_member183819
Active Contributor
0 Kudos

Hi

check SC - display changes via monitor sc

check PO - history data

some thing is wrong in your PO .

br

muthu

Former Member
0 Kudos

Hi all.

I have checked the PO and SC history . I couldnt find anything strange.

Could you please tell me any other option's , why we cannot do confirmation.

Former Member
0 Kudos

just try in your backbend system do a MIGO 101 to see if it's let you enter a goods receipt, that way we can isolate whether the issue with particular PO or with SRM .

Thanks

TP

Former Member
0 Kudos

Hi Muthu,

I have checked the PO and SC history . I couldn't find anything strange in the history.

Kindly let me know the specific point to check .

Its very strange,which we are facing.

Thanks.

Former Member
0 Kudos

HI

Please check for external search is active or nor if it is active then you cant able to do the grn.

Check partner error for the this confirmation.

As muthu told check in bbp_document_tab .

and any tRFC struck for this PO in WF.

Regards,

Satish.

Former Member
0 Kudos

Hi All,

thanks for all your support. The problem is the PO output was not yet prepared though its in ordered status.

After the output got created, customer able to post confirmation sucessfullly.

Former Member
0 Kudos

Hi,

Also you need to check whether the PO has Performance of Goods receipt indicator ticked .

Regards,

Sheeetal.

former_member183819
Active Contributor
0 Kudos

Hi

What is the status of Purchase Order - that is important .

for eg. in classic PO can not be searched in SRM fr good receipt untill it released.

br

muthu