Workitem is running quite a long time

Former Member
0 Kudos

Hi There,

In my custom workflow I have one item running from a long time. There is a custom method assigned to this task and to be executed in background.

Please suggest me how I can stop this and rerun the same step.

regards,

Rams.

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

There must be some problem in your custom method , like infinite loop.

Check if you are getting entry in SM50 [Backgroud entry] and then select that entry and Process-> cancel without core.

After that execute the method alone in foreground and find out the error.

Regards

Aman

Former Member
0 Kudos

Hi Aman,

Thanks for your reply.

I couldn't find any background processors running in SM50. Can I stop the workitem and reprocess it?

regards,

Rams.

Former Member
0 Kudos

Execute RSWEWWDHMSHOW and check if you can cancel the background process.

Former Member
0 Kudos

Hi Aman,

Below job was not schedulded/run on that day.

regards,

Rams.

Former Member
0 Kudos

Check with Basis persons if they can help you out to terminate the process.