Dear All
We are working on a maintenance project and it will be strictly monitored on hourly basis activities. The problem we are facing is when the project is scheduled the time duration of some activities differ from their respected assigned WBS element. Scheduling scenario is bottom up and the desired result is that the exact duration of activity must copy to assigned WBS element.
Following is the detail of actual scenario:
Activity start date and time: 02.11.2009 u2013 10:00:00
Activity finish date and time: 03.11.2009 u2013 10:00:00
Total Duration =24 Hrs
But WBSE shows:
Start and finish time: 02.11.2009 u2013 03.11.2009
Total Duration WBSE: 2 Days
What we need is 1 day in WBSE OR if activity is of 42 hours then WBSE should show 1.75 days and Gantt chart should show same length bar of both WBSE and Activity, Otherwise it will reflect the wrong analysis.
Please advice.
Thanks
Atif
Edited by: Atif12 on Nov 4, 2009 10:41 AM
Please check the factory calender assigned in your activity & WBS element.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
85 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.