11-04-2009 7:55 AM
Hi,
We use Fund Management and Material Ledger in ECC 6.0.
Posting goods receipt for material with price control S (Standard price) were successful, but whenever we post goods receipt for material with price control V (Moving average price), the following error comes up:
No commitment items selected
Message no. FI606
System Response
No commitment items selected
What might be the problem?
The account assignment in MIGO view are already filled with fund center and commitment item number automatically
We already assigned all that can be assigned in FMDERIVE (material to comm item, plant to comm item, gl to comm item, etc)
We also already check OSS notes: 939545, 148967, 1312483, 164077
Please help
Thanks
11-04-2009 11:23 AM
Hi,
Try putting a trace on the FMDERIVE and see what the results are.
Regards,
Eli
12-28-2009 9:05 AM
Ok I have found the solution. i just need to create a comittment item with Financial transaction: 40. Strange though, we dont use category 40.