on 11-03-2009 10:39 AM
Dear Experts.
I have come across a unique scenario where i have a WBS element which is carrying actual cost and commitment cost in it. Now the user needs this WBS element to be transfered to other operative project.
Do we have any way where we can transfer this WBS element without affecting the cost in it. Even we are not using any settlement in this project.
is there any way we can tranfer with or without the cost in it.
Reply at the earliest will be appreciated!
Thanks and Regards
Praveen B M
Hi,
I suggest, you can create a required WBS in the relevant project and do the actual cost transfer using KB11N (WBS to WBS option). For committments you just need to change the account assignment in the origin object to the new one. Do mark the current WBS as closed and keep it to address the reporting requirements in future.
Regards,
Neeraj
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.